I will be updating the information on the main web site as time permits.
We have today submitted plans to our local council in Western Australia to build a 13m x 7m (42′ x 23′) Garage to house the Denver’s RailRoads layout. If approved I can set up the old Denver’s RailRoads layout, which measured 12m x 6m, without any changes to the basic plan. However the extra one meter (39″) to both the length and width means that I can make the following enhancements to the layout:
For the last eight months or so our house has been up for sale and finally it sold late in 2019. My wife wanted to move to a colder, less humid, climate and we agreed on Mandurah, just south of Perth in Western Australia, where I have family (and help lifting layout modules). As part of our negotiations it was agreed that we would buy a house and land big enough to house my 12m x 6m layout as is. That was easier said than done but we have now purchased a 1991 square meter block of land which according to the Mandurah city councils web site should mean that I can build a 13m x 7m garage, not only large enough to house the old layout but also large enough to allow me to extend the layout where it needs it (in the Denver freight yard) and to increase the width of the center aisle.
The following photos are of the removal of the “mountain” module (Gore Canyon) from my garage and into the 20′ container. There were 8 modules in total loaded into the containers. Only this module and one other are without legs. Both are inner modules that do not form part of the continuous run around the outside. So it should be fairly quick and “easy” to reconnect the modules that run around the outside and have an operating layout. The inner modules can be added at a later date.
View from the back.
View from the side.
View from the front before we realised that to get it into the container with a minimum of fuss we would need to take the legs off.
Legless module going up the ramp and into the container
A bit more in.
And more.
And even more.
And finally into the container. Now we have to start thinking about getting it out and back on to it’s legs!
A little while ago I decided to build a 6′ x 2’6″ N Scale test track. The following are my initial observations.
The primary objective was to be able to test run locomotives and cars in a continuous circle and to change the DCC loco code from the default of “3” to the loco road number.
There were many secondary objectives including:
As my NCE Power Pro Radio system was wired to the main layout I used my backup NCE Power Cab system to run the test layout.
Initial conclusions:
As a result of the above I only intend to use the Kato layout for its primary purpose of test running locomotives and cars in a continuous circle and to change the DCC loco code from the default of “3” to the loco road number.
However I may well add scenery and make the layout into a display layout. There are two industry tracks, a two track yard and a railway station track. There are plenty of shunting options and for the future it could be used to test the “Ship It” system. Allowance has also been made for a Wye track so as locos can be turned.
With regard to the best method of operating a layout in terms of turnouts, block occupation and signals, there seems to be 3 options:
Since starting to write this blog I have spent a lot of time on Google and YouTube investigating Signal Systems. Most either require JMRI, Arduino scripts, infra-red track detection (I only want to use Current Sensing devices like NCEs BD-20) or very complicated DIY designs. I have also noted that at least two (Team Digital and Iowa Scaled Engineering) Signal Systems which showed promise, in terms of what I am looking, for had discontinued their products.
However Circuitron (of Tortoise fame) appear to have circuit boards that might fit my requirements, which are simply to be able to change 3 colour signals using BD-20 block detectors and either Gaugemaster GM500 latching relays or standard relays. Consequently I have ordered the following Circuitron products:
Once these products arrive I will be able to test them to see if they perform the Signaling functions I am hoping for. We shall see.
OK. All of the track laying for phase II is finished, which is a good thing given that I only have a dozen pieces of flex-track left.
I am now deep into the wiring of the motors in Denvers yards (what was phase four) while John is finishing installing SEEP point motors on the main line past the East Denver Belt line leading into Denver’s yards from Glenwood Springs (the old phase two).
Once we have all of the point motors wired up we can concentrate on the BUS wiring, which is complicated in Denvers yards as there is a return loop which will require a PSX reversing unit.
Finished installing the last of the turnouts in D&RGWs North Yard last night. Only have the 4 service tracks and 2 industry tracks left to lay.
Then it is onto wiring, wiring and a lot more wiring. Model RailRoading is fun! Still I am looking forward to constructing the control panels. Best part (together with scenery) of the hobby for me.
New areas to explore include controlling main line turnouts via DCC and installing signals. I found a really nice 3 light Chinese made N Scale signal (3 pack) at Amazon for only $11AUD each. Normally N Scale signals cost around $30 each so I have 27 more in transit to me. Plus I have 20 Drawf N Scale Signals (in packs of 10) coming for installation at DUT as part of Phase III.
Thanks to the hard work of Rod and John all of the Denver Union Terminal (DUT) tracks have been laid and SEEP turnout motors have been installed – wired and tested – under the baseboard. Now onto the laying of the tracks for C&S’s Rice Yard and the passenger coach yards.

This photo was taken 4 days ago. Since then I have laid a further 3 turnouts to the Holcim Cement and Hadley Auto Transport industry tracks in D&RGWs North Yard. These tracks will also act as Rio Grande Motorway tracks as required. That leaves 3 more turnouts for the D&RGW/Rock Island locomotive servicing tracks and the Pikestuff Small Enginehouse.

Then I can connect the remainder of the Kato extender tracks across the module 6 & 7 divide, patch up a couple of broken tracks and start making connections to the control panels, starting back at Black Hawk. Once all of the feeders are connected to the BUS it should be possible to run a train around the loop.
I have updated the main web site to reflect the 4 phases, instead of 5, of the layout construction mentioned in the last post.
The main line between Glenwood Springs and the Wye at Denver Union Terminal (DUT) is almost complete. I just have to install the Wye track to the north of DUT, (the connection to the east is already laid), and relay two or three turnouts on the main at the Prospect Junction end of North Yard. Then I can connect the remainder of the Kato extender tracks across the module 6 & 7 divide, patch up a couple of broken tracks and start making connections to the control panels, starting back at Black Hawk. Once all of the feeders are connected to the BUS it should be possible to run a train around the loop.
The changes to the Phase numbers will be reflected in the main web site pages in the fullness of time. Reducing the number of Phases to four will align with the planned N-Scale magazine articles.
Although some weeks have gone by, little has changed since the November update. The magazine article has been completed and should be published in the May/June edition of the N-Scale magazine. Rod is still working hard on pre-wiring the turnout motors for Phase III – Denver Union Terminal (DUT). Both John and Rod are currently on holiday.
I have made a breakthrough with the installation of KATO extender tracks between the Belt Line module and the North Yard module in Phase II. I have successfully installed Kato extenders on 4 tracks which paves the way for continuous loop train running. However when I went to lay more track in the yards I realised that because the module is against the wall it will not be possible to install point motors from underneath the baseboard because you cannot reach or see the top of the tracks. It is ok to “pop-up” the baseboard for BUS wiring. Consequently I have began to raise up the turnouts, one by one, and install PECO point motors attached to the turnouts. This has the advantage that once track laying is complete, wiring the turnouts to the control panels is a relatively quick job.
Once the yard tracks, turnouts and motors are installed I will work backwards along the main line to Glenwood Springs. With regard to the mainline all of the turnouts are to be computer controlled, which means that a number of DCCconcepts AD-S8sx decoders will need to be installed, together with NCE BD-20 block detectors. The Grand Junction loop turnouts will also have to be rewired with AD-S8sx decoders and 14 more NCE BD-20 block detectors added. Once complete testing with JMRI Panel Pro and Railway & Co can commence.