Progress since last update:
Due to the size and complexity of the new enlarged Coors Golden branch the sequence of track laying has been changed to the following:
Finally finished installing all 7 staging tracks (holding 14 18 car trains) at the Grand Jct. return loop which means that both the Rio Grande and CB&Q/UP main lines have been installed, leaving only the track for 9 branches and industry groupings to be laid.
Removed part of the scenery divider thereby making it possible to expand the Coors Brewery trackage by 150% whilst eliminating the Glenwood Springs Industrial area which was not prototype based.
Before:
After:
Coors Brewery now has 8 separate buildings:
Current Action through January 2024
Progress to date and 2024/25 Action Sequence
Going well. As at 19th November 2023 — Progress is as follows:
Action since June 27, 2023:
Immediate Action:
Planning Change:
Based on a number of operational layouts I have been viewing on YouTube of late, in order to start operations earlier than currently planned, I should build the RG North Yard and CBQ 38th Street Yard next.
This would include building the DUSTY Stockyards, Commerce City and the North Yard industries. I have sufficient stock of track, cork and turnouts to complete this task without a significant expense. There are very few operational issues in this build and once complete would enable operations by using the already laid South Denver loop track as DUT and roots south.
Once complete this would enable an Operating Freight and Passenger Layout between Denver North Yard and Grand Junction Loop & Staging Tracks.
Once complete the following urgent actions would be:
Action since June 22, 2023:
Immediate Action:
Big Picture Tasks for Action — once the immediate tasks have been actioned:
Next Phase: Activate DUT, South Denver, Joint Line Loop & Staging Tracks
Actioned since May 24, 2023:
Immediate Action:
Big Picture Tasks for Action — once the immediate tasks have been actioned:
Actioned since 10th May 2023:
Immediate Action:
Ongoing Action: