Going well. As at 19th November 2023 — Progress is as follows:

  1. D&RGW North Yard Classification tracks:
    • Cork laid Completed
    • Track laid Completed
  2. North Yard Locomotive facilities:
    • Cork laid Completed
    • Turnouts laid
    • Track laid
    • Kits built
  3. Cargill, Alpine and RG Motorway Industries:
    • Cork laid  Completed
    • Track laid
    • Kits built
  4. Denver Union Stockyards:
    • Cork laid Completed 
    • Track laid
    • Kits built
  5. C&BQ Classification Yard – using Kato #4 turnouts:
    • Cork laid  Completed 
    • Kato turnouts Completed
    • Track laid Completed
  6. Commerce City Industries:
    • Cork laid  Use Kato Set-Track
    • Track laid
    • Kits built
  7. Grand Junction Loop:
    • Cork laid  Completed
    • Kato 19″ Set-Track Curves Just started to lay
    • Turnouts laid
    • Track laid
  8. Craig Branch:
    • Cork laid Completed
    • Track laid
    • Kits built
  9. Glenwood Springs Industries:
    • Cork laid  
    • Track laid
    • Kits built
  10. Coors Brewery and Golden Branch:
    • Cork laid  
    • Track laid
    • Kits built
  11. Ford Motor & East Denver Belt Line Lead Tracks:
    • Cork laid Completed
    • Track laid
  12. Repair the Joint Line Return Loop trackage